PRYOR - LSB Industries Inc. expects more delays before it resumes operations at its main ammonia processing plant in Pryor, the company said Monday.
The Oklahoma City-based company shut down the Pryor plant in November for unplanned maintenance and to install new equipment.
LSB initially said the outage would last six to eight weeks. The company has finished repairs at the plant, but the delivery of a key part of a compressor that LSB needs to finish upgrades has been delayed.
The delay will push back the reopening of the plant by about four weeks, the company said Monday.
Click here to read the complete article at NewsOK.com.
Original Print Headline: Restart of Pryor ammonia plant about 4 weeks away